02. july, 2002

2002.

Project implementation time:

2002

Project promoter:

Liepāja Special Economic Zone Administration

The purpose of the project:

to ensure the compliance of Liepāja port with the requirements of national and international conventions and recommendations by building compliant, safe and efficient facilities for the reception and treatment of polluted waters generated by ships

Total cost of the project:

0.8 million EUR

Within the framework of the project, the construction of facilities for the reception and treatment of oil-contaminated waters of the port of Liepāja was carried out.

The works were carried out by SIA "Eko Osta". The project was completed in 2003.