“Business service structure territory and their public infrastructure development in Liepaja”
Project execution period:
Year 2014 – 2015
Project initiator:
Liepaja City Council
Purpose of the project:
To carry out reconstruction of streets and related underground engineer networks, and improvement and adjustment for entrepreneurship of their adjacent industrial territories in Liepaja
To enlarge territories suitable for entrepreneurship and to improve accessibility of these territories thus improving both town and region’s economic growth by also improving the urban environment, as well as thus creating preconditions for introducing new jobs, the following development measures were carried out within the framework of this project:
Within the framework of reconstruction of the business service structure territory, the following work was carried out:
• Reconstruction of Dūņu street pavement;
• Construction of bicycle road and sidewalk on Meldru un Dūņu streets;
• Recovering of the industrial territory;
• Construction of urban waste water and rainwater sewage, water pipe and drainage construction by observing Regulatory framework of the entrepreneurship support control;
• Construction of the street light in Dūņu street;
• Construction of the street light (road signs, horizontal designation).

Construction work was carried out by Ltd. ”Ceļu, tiltu būvnieks”; technical design was carried out by Ltd. “VCI”.

Total project costs: 1.6 million EUR, including 1.3 million EUR of co-financing from the European Regional Development Fund.
Within the framework of reconstruction of the business service structure territory the following work was carried out:
• Pavement reconstruction and construction;
• Bicycle road and sidewalk construction;
• Street light construction;
• Construction/reconstruction of rainwater draining collector and drainage construction;
• Reconstruction and construction of water pipe and urban waste water sewage by observing Regulatory framework of the entrepreneurship support control;
• Construction of the street light (road signs, horizontal designation).

Construction work was carried out by Ltd. ”Ceļu, tiltu būvnieks”; technical design was carried out by Ltd. “VCI”.

Total project costs: 2.8 million EUR, including 2.3 million EUR of co-financing from the European Regional Development Fund.
Within the framework of partial taking down of buildings and recovering of the territory in Zemgale and Virssardze streets the following work was carried out:
• Dismantling of buildings, groups of buildings and underground constructions;
• Cleaning of the territory from construction waste, pavement areas, waste and non-precious trees and bushes;
• Levelling of land plot relief;
• Laying of lawn in the unoccupied territory.

Construction work was carried out by Ltd. ”A-land”; technical design was carried out by Ltd. “”Arhitekta G.Vīksnas birojs””.

Total project costs: 0.6 million EUR, including 0.5 million EUR of co-financing from the European Regional Development Fund.